Yuanda Electric recently released a customer case: In the Aviation City · Lanyuan electrical equipment procurement project, the contractor Shaanxi Yuanda Complete Equipment Electric Co., Ltd. completed the production and supply of ring main units, harmonic elimination devices, integrated power supplies, electric energy metering boxes and other equipment according to the contract list. All relevant equipment has been delivered to the site and passed the incoming inspection and acceptance, meeting the installation and use requirements.
Project background: Aviation City · Lanyuan electrical equipment procurement
The employer of the Aviation City · Lanyuan electrical equipment procurement project is Xi'an Liangli Electric Power Group Co., Ltd., and the contractor is Shaanxi Yuanda Complete Equipment Electric Co., Ltd.The project centers on the procurement of electrical equipment for the park, involving ring main units, harmonic elimination devices, integrated power supplies, electric energy metering boxes and other types of equipment.As the contractor, Yuanda Electric organized production and supply according to the contract list to ensure that the equipment categories and specifications match the project requirements.
- Employer: Xi'an Liangli Electric Power Group Co., Ltd.
- Contractor: Shaanxi Yuanda Complete Equipment Electric Co., Ltd.
- Project content: Produce and supply ring main units, harmonic elimination devices, integrated power supplies, electric energy metering boxes and other equipment according to the contract list
Scope of supply: production and delivery organized according to the contract list
During project execution, Yuanda Electric strictly followed the requirements of the contract list to organize production and arrange supply of equipment such as ring main units, harmonic elimination devices, integrated power supplies, and electric energy metering boxes.The equipment categories cover links such as power distribution, power quality, and metering, reflecting the company's comprehensive capability in the supply of complete sets of electrical equipment.All equipment was produced as agreed in the contract and delivered to the project site, providing equipment assurance for subsequent installation and use.
- Ring main unit: key equipment used in power distribution networks
- Harmonic elimination device: used for power quality control
- Integrated power supply: provides power support for related systems
- Electric energy metering box: used for electric energy metering management
Incoming inspection and acceptance: The equipment meets installation and use requirements.
After the equipment arrived at the site, the relevant project parties organized incoming inspection and acceptance work.Upon inspection, the ring main units, harmonic elimination devices, integrated power supplies, electric energy metering boxes, and other equipment supplied by Yuanda Electric met the requirements of the contract list, passed acceptance, and met installation and use requirements.This result reflects Yuanda Electric's control capability in equipment production quality and supply contract performance, and also provided a qualified equipment foundation for the subsequent installation phase of the project.
- All equipment has been supplied and delivered to the site.
- Incoming inspection and acceptance passed.
- The equipment meets installation and use requirements.
Case value: Supply practice centered on contract performance
This case of the electrical equipment procurement project for Aviation City · Lanyuan fully demonstrates Yuanda Electric's fulfillment capability in the field of complete electrical equipment supply.From production according to the list to delivery to the site, and then to passing the on-site inspection and acceptance, all stages were carried out around the contract requirements, ensuring the timeliness and compliance of equipment supply.For similar park electrical equipment procurement projects, this case also provides referable practices for supply organization and quality control.
- Strictly organize production and supply according to the contract list
- After the equipment arrived at the site, it successfully passed the on-site inspection and acceptance
- Provide qualified equipment assurance for project installation and use
Follow-up arrangements
Yuanda Electric will continue to take contract fulfillment as the cornerstone and provide reliable complete equipment supply services for various electrical equipment procurement projects.This case only covers the equipment supply and on-site acceptance stages; subsequent progress such as installation and commissioning, project completion, and power transmission and commissioning shall be subject to the actual project arrangements.